The Project I Staffed Wrong From the Start
I hired a subcontractor based on a vague sense of how long the work would take. It went badly.
I brought someone in to help with a project because I was busy and the client needed things faster.
I did not give her a clear hour budget. I told her the deliverables. I told her the deadline. I assumed she would work at roughly the pace I would work, because I had no actual data on her yet and I had no actual data on myself for this type of work either.
This was the first mistake, and it had two parts.
The Budget I Never Set
I quoted the client a flat rate. I had done similar projects before and had a rough sense of what they took. I allocated about sixty percent of the fee to my subcontractor and kept the rest as my margin for oversight and delivery.
What I did not do was look at my own time logs from previous similar projects before I set that budget. I had the data. I had been tracking for over a year. But I was moving fast and I estimated from memory instead.
Memory said those projects took about twenty hours total. The logs, which I pulled later, said they averaged twenty-nine.
Nine hours is a significant gap when you are staffing a project.
What Happened to the Subcontractor
She worked more hours than the budget I had mentally assigned her. She did not know there was a budget because I had not told her explicitly. She was thorough. She asked good questions. She did the work correctly.
When she sent her invoice, it was about forty percent higher than what I had planned for.
I paid it. It was not her fault. She had done the work, done it well, and had no way to know she was running over a budget I had never communicated.
My margin on that project effectively disappeared.
What I Should Have Done Before Anyone Started
Set a clear hour budget for the subcontractor based on actual data, not a guess.
That means pulling previous project logs before staffing anyone. If I had seen that similar projects averaged twenty-nine hours, I would have allocated differently. I might have quoted the client more. I might have scoped the deliverables tighter. I might have adjusted what I asked the subcontractor to do.
Any of those options would have been better than what happened, which was absorbing the cost silently and feeling resentful about a situation I had created.
I also should have told her the budget explicitly. Something simple. Something like: I am allocating fifteen hours for your portion. Let me know if you think that is tight before you start. That conversation would have surfaced the problem before it became an invoice.
What I Changed
Every time I bring someone in now, I pull the time log from a comparable project first. I look at how the hours actually split across phases. Then I give the subcontractor a written hour estimate and ask them to flag me before they hit it if they think they are going over.
It is not bureaucratic. It takes about ten minutes. It has saved me from two more versions of that same mistake.
I also started tracking my own coordination and oversight time on subcontracted projects separately. That time adds up. It is real work. For a while I was treating it as free because it felt like management rather than billable output. It is not free.
If you are going to staff projects well, you need to know what the work actually costs before you price it and before you delegate it. The data is usually sitting in your logs already. You just have to look at it before you start, not after everything goes sideways.
Track your time, bill every minute.